The project formally commenced in July 2013. However, given the complexities of the issues that need to be addressed for Ingleside and the iterative nature of the process, delays to the program have unfortunately occurred.

Key Milestones


Prior to formal Community Launch of Precinct Plan project

 

Timing

 Establishment of Project Control Group (PCG)Completed - July 2013
 Project Plan (Community Engagement Strategy) & Probity Plan endorsed by PCGCompleted - July 2013
 Community Engagement Tools for formal launchCompleted - July 2013

Formal Commencement – Precinct Plan project

 Launch – Information SessionCompleted - July 2013
 Community Information SessionCompleted - Aug 2013
 Ingleside Community Reference Group – Community members selectedCompleted - Sept 2013

Ingleside Precinct Plan Project

 Appointment of consultants to undertake studies which will provide detailed evidence about issues and constraints and will inform the rezoningCompleted - Oct 2013
 Commencement of studies to inform precinct planningCommenced - Nov 2013
 Ongoing consultation with other government agencies and service providersCompleted - March 2014
 Enquiry by Design Workshops - Round 1 WorkshopsCompleted - March to Oct 2014
 Preparation of potential land use arrangements based on preliminary technical findingsCommenced - Nov 2014
 Enquiry by Design Workshops - draft Structure PlanCompleted - Late 2014
 Prepare and refine the draft Structure Plan, draft zoning and development controls based on technical evidence and feedback from our enquiry by design workshopsCommenced - Late 2014 to late 2015
 Survey for the Angus Onion OrchidCompleted - Sept/Oct 2015
 Report back to the Ingleside Community Reference Group on the findingsCompleted - 8 Dec 2015
 Consultation on draft Structure Plan and technical studies before formal  
 Review of submissions2018
 Bush Fire Risk Assessment undertakenLate 2018
We are hereCommissioning and undertaking a bush fire evacuation study2019
 Outcomes of evacuation study assessed Late 2019
 Assessment of development potential at Ingleside and development of appropriate planning pathwayEarly 2020

The outcome of the above will determine the future program.

Please Note: The development capacity will be dependent on outcomes of the bush fire evacuation study, which will inform the future program.


 

Connecting Northern Beaches

Find out the progress of the spectacular 36km Northern Beaches Coast Walk stretching from Manly to Palm Beach

walkway.jpg

Warriewood Community Centre

We’re building a new multi-use community centre on the existing site of the Nelson Heather Centre on the corner of...

A_Warriewood_Community_Centre_-_View_from_Boondah_sports_fields_snip.PNG

Pipeline Active Transport Corridor

The $7.2m Pipeline Active Transport Corridor project will provide a 9.2km shared user path from Beacon Hill to St Ives...