Images

The project formally commenced in July 2013. However, given the complexities of the issues that need to be addressed for Ingleside and the iterative nature of the process, delays to the program have unfortunately occurred.

Key Milestones


Prior to formal Community Launch of Precinct Plan project

 

Timing

  Establishment of Project Control Group (PCG)Completed - July 2013
  Project Plan (Community Engagement Strategy) & Probity Plan endorsed by PCGCompleted - July 2013
  Community Engagement Tools for formal launchCompleted - July 2013

Formal Commencement – Precinct Plan project

  Launch – Information SessionCompleted - July 2013
  Community Information SessionCompleted - Aug 2013
  Ingleside Community Reference Group – Community members selectedCompleted - Sept 2013

Ingleside Precinct Plan Project

  Appointment of consultants to undertake studies which will provide detailed evidence about issues and constraints and will inform the rezoningCompleted - Oct 2013
  Commencement of studies to inform precinct planningCommenced - Nov 2013
  Ongoing consultation with other government agencies and service providersCompleted - March 2014
  Enquiry by Design Workshops - Round 1 WorkshopsCompleted - March to Oct 2014
  Preparation of potential land use arrangements based on preliminary technical findingsCommenced - Nov 2014
  Enquiry by Design Workshops - draft Structure PlanCompleted - Late 2014
  Prepare and refine the draft Structure Plan, draft zoning and development controls based on technical evidence and feedback from our enquiry by design workshopsCommenced - Late 2014 to late 2015
  Survey for the Angus Onion OrchidCompleted - Sept/Oct 2015
  Report back to the Ingleside Community Reference Group on the findingsCompleted - 8 Dec 2015
  Consultation on draft Structure Plan and technical studies before formal exhibitionDecember 2016 to February 2017
We are here  Review of submissionsFollowing consultation
  

Public Exhibition of draft planning controls (including section 94 plan, statutory controls biodiversity certification package)

late 2018
  Review of submissionsFollowing Public Exhibition
  Gazettal of final Precinct PlanFollowing Public Exhibition
  Development can beginFollowing Rezoning

Please Note: The timing will be dependent on outcomes, any approvals necessary for public exhibition and future rezoning