The project formally commenced in July 2013. However, given the complexities of the issues that need to be addressed for Ingleside and the iterative nature of the process, delays to the program have unfortunately occurred.
Key Milestones
Prior to formal Community Launch of Precinct Plan project
Timing | ||
Establishment of Project Control Group (PCG) | Completed - July 2013 | |
Project Plan (Community Engagement Strategy) & Probity Plan endorsed by PCG | Completed - July 2013 | |
Community Engagement Tools for formal launch | Completed - July 2013 |
Formal Commencement – Precinct Plan project
Launch – Information Session | Completed - July 2013 | |
Community Information Session | Completed - Aug 2013 | |
Ingleside Community Reference Group – Community members selected | Completed - Sept 2013 |
Ingleside Precinct Plan Project
Appointment of consultants to undertake studies which will provide detailed evidence about issues and constraints and will inform the rezoning | Completed - Oct 2013 | |
Commencement of studies to inform precinct planning | Commenced - Nov 2013 | |
Ongoing consultation with other government agencies and service providers | Completed - March 2014 | |
Enquiry by Design Workshops - Round 1 Workshops | Completed - March to Oct 2014 | |
Preparation of potential land use arrangements based on preliminary technical findings | Commenced - Nov 2014 | |
Enquiry by Design Workshops - draft Structure Plan | Completed - Late 2014 | |
Prepare and refine the draft Structure Plan, draft zoning and development controls based on technical evidence and feedback from our enquiry by design workshops | Commenced - Late 2014 to late 2015 | |
Survey for the Angus Onion Orchid | Completed - Sept/Oct 2015 | |
Report back to the Ingleside Community Reference Group on the findings | Completed - 8 Dec 2015 | |
Consultation on draft Structure Plan and technical studies before formal | ||
Review of submissions | 2018 | |
Bush Fire Risk Assessment undertaken | Late 2018 | |
We are here | Commissioning and undertaking a bush fire evacuation study | 2019 |
Outcomes of evacuation study assessed | Late 2019 | |
Assessment of development potential at Ingleside and development of appropriate planning pathway | Early 2020 |
The outcome of the above will determine the future program.
Please Note: The development capacity will be dependent on outcomes of the bush fire evacuation study, which will inform the future program.
![]() | ![]() | ![]() |